Sod Turning Sham

All the dignitaries looked very happy at the the sod turning today. You would think that they had this whole deal wrapped up and the community behind them.

In the past week both the City and RM have cancelled several special meetings to approve tenders.

While apparently their lawyer is out of town, another Daily Graphic report mentions the project manager had some concerns about what was in the tender.

Unconfirmed reports have the tender amount well above the budget, so is that what the project manager had to change?

What was the rush to begin tearing down fences last week which caused disruptions to the Potato festival? Especially since there is no legal agreement in place yet with the Fair Board?

What about the Harness Races scheduled at the end of the month?

Did they have to show some progress to keep up the impression that things are going ahead?  With a Daily Graphic survey showing 93% of respondents will not donate any money to fundraising efforts, what does that tell you about community support?

Businesses that signed up for naming rights and other donations have already had angry customers refuse to continue doing business with them and moved their accounts or have chosen to take their shopping elsewhere. Once again, what does that tell you about community support?

Let’s not forget the many Portage residents who offered up donations of 10,000$ each, but only on the condition that the facility was moved to the Republic Park where every public survey and consultant reports have indicated it should go. That would have raised more money from local citizens than the Portage Recreation Committee has raised from private individuals in 3 years

If Premier Gary Doer thinks the NDP will garner enough votes in Portage with this pitiful handout, he is sadly mistaken. When 1400 people sign a petition in 4 days to Save the Island, I can’t imagine them voting for any provincial politician that helped the City/ RM pull off this scheme.

With the impending legal challenge and upcoming votes in City and RM councils, wouldn’t it be the prudent course to have everything in place before spending any more money? It would especially be the fiscally responsible way to do things

What is the rush?

Sod turned for PCU Centre

From The Portage Daily Graphic. ( Check out the link for a picture, this is the closest these guys ever get to real work )

With scenic Crescent Lake as a backdrop, officials from all three levels of government met at the fairgrounds on Island Park in Portage la Prairie Monday to announce funding for the PCU Centre, and officially turn sod on the project.

Manitoba Premier Gary Doer, along with Vic Toews, president of the Treasury Board, on behalf of Minister of Intergovernmental Affairs and Minister of Western Economic Diversification, Rona Ambrose, Portage Mayor Ken Brennan, and Toby Trimble, Reeve of the Rural Municipality of Portage, made the announcement to the crowd of nearly 200 people gathered at the future site of the sports multiplex.

The $35.7 million project will receive $10 million through the Canada-Manitoba Municipal Infrastructure Fund (MRIF) and an additional $1.7 million is being provided from the province’s Building Manitoba Fund.

The $10 million MRIF contribution is split equally between the three levels of government, and no new funding was announced at the ceremony.

Mayor Brennan said he was thankful to see the funding from the provincial and federal governments confirmed at the ceremony, and is eager to see construction get under way.

“We made a giant step forward today,” he said. “Turning the sod is ceremonial, but it does mean something.

“The project is going to go, it’s going to be successful and we’re going to have a great recreational multiplex.”

Multiplex land lease agreement still not finalized

From the Portage Daily Graphic

Portage RM council postpones approval as final wording fussed over by lawyers

Posted By Shane Gibson, The Daily Graphic

Posted 13 hours ago

A hastily called Rural Municipality of Portage la Prairie council meeting on Friday was supposed to give the proposed PCU Centre the green light to start construction — but the full gallery of citizens who came out in opposition were told the special meeting had been just as hastily cancelled.

Council had planned to approve the final agreement between the RM and City of Portage and the Portage Industrial Exhibition Association for a 99-year lease of the fairgrounds on Island Park to be used for the multiplex. The first of five tenders for the construction of the $35.7-million sports facility was also to be voted on at that short-notice meeting.

Reeve Toby Trimble explained to the roughly 16 surprised citizens in attendance the lease agreement was still in the hands of lawyers with a couple last-minute wording changes. He also said although the first tender came in within budget, council had a few wrinkles to iron out before voting on that as well.

“(The project manager) had some concerns about what was in and what was out of one of the tender packages, so he just wanted to talk to the bidder before we accepted it,” explained Trimble after the meeting.

After learning about the cancelled meeting, many of the residents voiced concerns about how much notice was given prior to the hearing.

The meeting had been advertised on the RM’s website since 4:30 p.m. on Aug. 13, fulfilling the municipal government’s requirement to give 24 hours notice of a public hearing.

Oakville area resident Dwayne Leslie questioned how fairly the RM gives public notices.

“We have to give 96 hours to come and speak (in front of council),” he noted in the council chamber. “It would be nice if you could at least give half of that to us, so we know what you’re up to.”

Sod-turning Monday for multiplex

From the Portage Daily Graphic

After months of debate at city hall and in coffee shops throughout Portage la Prairie, preliminary work has gotten underway on the construction of the PCU Centre.

A trailer has been set up at the location acting as the site office, construction crews have been busy building a safety fence around the 8.5 hectares of construction site, and the official sod-turning ceremony is scheduled for Monday.

“We’re really looking forward to this, for the community,” explained Portage Mayor Ken Brennan. “We know that the community has been waiting for this for decades, and it’s going to feel real good on Monday when we finally get this thing going.”

Officials from the federal, provincial and both municipal governments will be on hand at the ceremony to discuss their financial contributions to the project.

As well as the government funding, $3-$4 million of the $35.7 million the new multiplex is projected to cost will be provided by fundraising efforts from the Portage Recreation Committee (PRC).

The PRC will embark on the second of three fundraising phases this September. The second phase will see the PRC canvassing businesses, foundations and other organizations in the community for donations.

“The reason we didn’t do much through the summer, is because it’s just a lousy time to try and get people together,” explained PRC co-chairman Brian Gilbert. “Everybody is on holidays and businesses are under pressure because of staff shortages.

“By the time September hits everybody is kind of back down to a schedule and structure, and it’s a little easier to sit down and talk to these guys.”

The third and final fundraising effort will be started by the end of the year, and will involve going out into the community and asking individuals to donate money for the project, a feat that could prove to be difficult according to a recent unofficial web poll conducted by The Daily Graphic on its website, thedailygraphic.com.

The poll showed 93 per cent of those who responded would not contribute personally to the project, a fact that doesn’t concern Gilbert.

“I’m confident we’ll raise the money we need,” he said.

Special meeting that wasn’t

From the Portage Daily Graphic

A special council meeting of the Rural Municipality of Portage la Prairie, intended for 9 a.m. this morning, was cancelled suddenly, although 16-20 concerned citizens from the RM and the city were prepared to attend.

Many of them were there to witness the RM council’s plan to move forward with decisions regarding the new multiplex, which is about to begin construction at the Island Park fairgrounds.

The meeting was called, the reeve said, to vote on a long-term lease agreement with the Portage Industrial Exhibition Association and to approve the first tender for construction of the multiplex.

Reeve Toby Trimble said the meeting was put off to next week because the fair board’s lawyer is not available and the replacement lawyer did not feel comfortable with some of the items in the contract, and asked to wait for the primary lawyer’s return.

He also said the tender came in on budget, but there were still a few outstanding issues the project manager wanted to iron out.

In the place of the RM meeting, the RM council held an impromptu, 20-30 minute question and answer session for the citizens who had lined up outside the RM office this morning to attend.

A separate City of Portage council meeting was also scheduled for 10:30 a.m. Friday. The results of that meeting were not known by press time.

Short Notice RM Meeting

From a tiny link on the RM website

PUBLIC NOTICE is hereby given
that a Special Meeting of
Council has been called for Friday,
August 15th, 2008 at 9:00 a.m. in the Council
Chambers of the Rural Municipality of Portage la
Prairie to discuss the following items pertaining to
the multiplex recreation facility:

Tender 1 Package

Land Lease Agreement
Thank you.
Council of the Rural Municipality of Portage la Prairie

Sod Turning ?

A select group of people received this invite today.

The Province of Manitoba

and

The Government of Canada

with

The City and RM of Portage la Prairie

invite you to an announcement and sod turning

ceremony under the

Canada-Manitoba Infrastructure Program

Date: Monday August 18th, 2008

Time 3:00 PM

Location:  The Portage Fairground Just North of the Grandstand in the City of Portage la Prairie

For more information, contact:

Marcus Miller

Communications Coordinator

Canada-Manitoba Infrastructure Secretariat

Tel 204-945-8778 or 1-800-268-4883

What’s this ?

Looks like some action today at the fair grounds, it appears they are removing the chain link fence from around the racetrack and repositioning it around the outside of what will be the construction area.

I wonder how safe the track will be for the possible last Great Western Harness Racing meet scheduled for August 30-31 2008 ?

How can they start work without any tenders yet being accepted?

How can they start demolition when the Fair Board agreement has not been passed by either council ?

Why was the City’s special council meeting abruptly canceled just minutes before the scheduled start time today?

Is it because the first tender came in so over budget they don’t want the public to find out ?

Inquiring minds want to know……..

Portage Multiplex demolition begins

Multiplex sparks lawsuit

Posted From the Portage Daily Graphic Thursday July 31st

A group of ratepayers from the Rural Municipality of Portage la Prairie are taking their concerns over the RM’s funding of the proposed PCU Centre to court.

On Tuesday morning, a group of roughly 70 residents met with Grant Driedger, a legal representative with Smith Neufeld Jodoin Law Offices in Carman, to discuss their legal options.

“There’s a group of ratepayers from pretty much across the RM, who have significant concerns with the borrowing and the amount of funding that the RM is proposing to put into the multiplex,” explained Driedger after the meeting. “The concerns are both that it’s being done and also how it’s been done.

“At this point, we will be proceeding to bring a court application to get the court to take a look at how this has happened, and whether the RM has done what they needed to do.”

He said the main argument his firm will make in the application is that a new borrowing bylaw should be required from the RM because of the changes made in the multiplex’s plans.

“Initially, the proposal was two arenas, a competitive pool and various other things,” explained the lawyer. “When the cost figures came in higher than they initially expected, they had to scale that down considerably.

“So the bylaw that they’re relying on to authorize them borrowing money to

fund the project was based on Plan A, and now they’re going ahead with Plan

B, so they’re borrowing the same amount of money, but getting a significantly lesser facility.”

City approves extra money for redesign of multiplex

Posted from the Portage Daily Graphic Friday August 1st

Lowering the estimated costs associated with building the PCU Centre in Portage to an affordable level was not free for the City and Rural Municipality of Portage la Prairie.

The city will pay Stantec Architectural Ltd. an extra $215,135 plus tax for the work the company did redesigning the complex, after the initial costs came in over budget.

At a special council meeting held at city hall on Thursday, councillors voted in favour of the payment.

“When we had to reconfigure some of the components of the multiplex, they had to go back to the drawing board and do a lot of redesign,” explained Mayor Ken Brennan. “So this is the bill for our request for a redesign.”

When the original plans came in at a cost of nearly $42 million, Stantec scaled back the plans by removing the competitive pool and phasing in the second arena originally included in the plans for the project.

Brennan explained the additional costs of the redesign have already been included in the current estimate of $35.7 million needed to build the revised PCU Centre project.

The city’s approval of the payment is conditional on whether the additional design fee is approved by the RM of Portage, which has agreed to reimburse the city for one-third of the design costs for the project.

The RM will vote on the additional fee at its next council meeting scheduled for Aug. 5.